power supply Archives - Waking up in Geelong https://wongm.com/tag/power-supply/ Marcus Wong. Gunzel. Engineering geek. History nerd. Mon, 28 Oct 2024 22:58:27 +0000 en-AU hourly 1 https://wordpress.org/?v=6.7.1 23299142 Private security lighting on public poles https://wongm.com/2023/09/private-security-lighting-on-public-poles/ https://wongm.com/2023/09/private-security-lighting-on-public-poles/#comments Mon, 18 Sep 2023 21:30:00 +0000 https://wongm.com/?p=21392 Something odd I’ve noticed over the years is floodlights shining onto private property from public power poles. So who foots the bill for them? They’re a common sight in industrial areas. Their orange glow shining onto locked up warehouses. From atop power poles. But with no power meter to be found anywhere. And an answer […]

The post Private security lighting on public poles appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
Something odd I’ve noticed over the years is floodlights shining onto private property from public power poles. So who foots the bill for them?

'Watchman' security lighting shine on private property from utility owned power poles

They’re a common sight in industrial areas.

'Watchman' security lighting shine on private property from utility owned power poles

Their orange glow shining onto locked up warehouses.

'Watchman' security lighting shine on private property from utility owned power poles

From atop power poles.

'Watchman' security lighting shines on private property from utility owned power poles

But with no power meter to be found anywhere.

And an answer

Well, I finally found the backstory to these lights in the State Electricity Commission of Victoria’s 1989 annual report, under their list of electricity tariffs – it was a fixed service charge.

Security Lighting (Watchman Floodlighting)

Generally available to all customers, except private domestic premises, for all night security floodlighting of buildings, property, etc.

Initial charge per lamp
$150.50

Charge per month according to Lamp type/size as follows:

125W mercury
$8.75

250W mercury
$15.05

400W mercury
$21.30

150W sodium
$15.00

250W sodium
$18.00

400W sodium
$22.05

*Initial charge covers the provision, erection and eventual removal of the lamp.

The difference between sodium vapour and mercury vapour lamps is the colour temperature – yellow versus blue.

And that led me to Ergon Energy in Queensland, also uses the ‘Watchman’ lighting brand.

Watchman lights are different to street lights. Street lights are used to illuminate public thoroughfares such as streets and roads. Watchman lights can be used for security or safety to illuminate areas such as public parks, private car parks, and pathways.

Watchman lights are installed and maintained by us. We will be able to advise you on the type and size of watchman light you might need once we receive your connection enquiry or application.

Watchman lights are usually connected to our network via an unmetered supply (UMS) connection, meaning it doesn’t need an electricity meter. This is because the electricity usage is predictable or can be accurately calculated without a meter.

And despite the privatisation of Victoria’s electricity network, the ‘Watchman Floodlighting’ name is still used today by Powercor.

Agreement for the Installation of (Watchman) Security Floodlighting

An Installation Charge will be payable for each light prior to installation. This installation charge applies to
each light and excludes ongoing charges applied by the electricity Host Retailer.

LED medium output
$ 2,597.10

LED high output
$ 3,115.20

That’s some massive cost inflation!

So who foots the power bill?

Officially, these lights are considered a “franchise unmetered load“:

electrical installations that are connected to the distribution network without an energy meter and must purchase the energy through the respective local retailers. Examples include bus shelter lights, public phone booths, traffic lights and some public electric barbecues.

Or an “unmetered supply“:

The power supply to lighting is not metered. Instead, distributors bill Council with an estimated average of energy consumption per light multiplied by total number of lights and hours of usage. The estimated average is a scientifically determined standard for each light type, agreed to by the regulator and published in ‘load tables’

So the beneficiary of the watchman lighting has to pay a monthly charge, but can’t choose their energy retailer.

In most cases, you can’t switch retailers with an unmetered supply.

Most unmetered supplies (UMS) are linked to a specific retailer based on location and the distribution patch you’re in. There are some exceptions, for some devices. You’ll need to ask your retailer about your particular UMS device.

But there is an incentive to audit these lamps, as sodium vapour and mercury vapour fixtures are costly to run. In 2020 the City of Merri-bek audited the ‘watchman’ lights paid for by Council, upgrading some lights while removing those no longer needed, achieving estimated savings of $30,000 a year and 100 tonnes of carbon emissions.

Further reading

The ‘Flood Lighting’ section of the Queensland Public Lighting Construction Manual has examples of ‘watchman’ floodlight installs.

Post retrieved by 35.215.163.46 using

The post Private security lighting on public poles appeared first on Waking up in Geelong.

]]>
https://wongm.com/2023/09/private-security-lighting-on-public-poles/feed/ 3 21392
“This power pole belongs to” https://wongm.com/2023/02/this-power-pole-belongs-to-signage-melbourne-victoria/ https://wongm.com/2023/02/this-power-pole-belongs-to-signage-melbourne-victoria/#comments Mon, 06 Feb 2023 20:30:00 +0000 https://wongm.com/?p=20837 At primary school they tell parents “label everything”. But slapping a “this pole belongs to [power company]” sign seems like overkill – who is going to steal a bloody power pole planted into the ground? But there is a reason behind these signs – and Jeff Kennett is to blame. In the beginning, the State […]

The post “This power pole belongs to” appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
At primary school they tell parents “label everything”. But slapping a “this pole belongs to [power company]” sign seems like overkill – who is going to steal a bloody power pole planted into the ground? But there is a reason behind these signs – and Jeff Kennett is to blame.

'This pole belongs to Jemena' plaque on a power pole in Powercor territory - Ballarat Road, Braybrook

In the beginning, the State Electricity Commission of Victoria (SECV) was responsible for the generation, transmission and distribution of electricity over the entire state of Victoria.*

(Well, *almost* all of it.)


SECV annual report 1972

But then in the 1990s Jeff Kennett carved up the SECV into a web of different generation, transmission and distribution business – ready for privatisation.

The responsibility for the distribution of electricity to individual consumers was split into five geographic regions – CitiPower supplying the Melbourne CBD; United Energy and Jemena the middle suburbs; and Powercor and SP AusNet from outer suburbs of Melbourne and into the Victorian countryside.


Essential Services Commission diagram

But how do you draw the line between the different electricity distribution businesses?


Map from www.energy.vic.gov.au

You follow the power lines.

Paperbark tree with the middle chopped out so that it's clear of power lines

Based on how the SECV originally structured their distribution network.


Essential Energy diagram

Zone substations convert electricity at 66kV down to 22kV, and you can hide one on a suburban street – there would be about a hundred of them scattered around Melbourne alone.

Corio Zone Substation converts 66 kV to 22 kV in North Shore, Geelong

But zone substations need to be supplied with power, which comes from much larger terminal stations. You can see their massive 220 kV transmission lines from a mile away, so there are only a dozen around Melbourne.

Geelong Terminal Station on Anakie Road

Which leads us back to the “this pole belongs to [power company]” signs…

'This pole belongs to United Energy' sign in Surrey Hills

Turns out some zone substations have 66 kV power lines that pass pass through areas that belong to other distribution companies on their way to the nearest terminal station, so the signs are needed so the two companies know who is responsible for maintaining a given pole.

And another mess

In the Victorian electricity industry the 1990s reforms there is a second market subject “competition” – multiple energy retailers all competing to sell you the exact same electrons to you, but at wildly different prices.

All electricity retailers in Victoria are required to give consumers a “Default Offer” – a fixed price set by the government which is considered to be reasonable to both parties.

Unfortunately there is one part you don’t get a choice in – each of the five energy distributors set their own ‘daily supply charge’ which all retailers have to pass on to you.

As of 2023 people living in the United Energy region only pay $1.0753 per day to have an electricity connection, while those in the Powercor area get slugged $1.3102 per day.

You’d hate to be right on the boundary of two distributors, and living on the side that has to pay more!

As for a real solution?

The other solution would be to ditch this whole charade of “competition” and just nationalise this mess of separated distribution and retail electricity utilities.

When I first tweeted this back in mid-2022 I was hoping we’d eventually see a political party with the guts to do that, and a few months later, one came close – promising to deliver “government ownership of energy generation”.

Post retrieved by 35.215.163.46 using

The post “This power pole belongs to” appeared first on Waking up in Geelong.

]]>
https://wongm.com/2023/02/this-power-pole-belongs-to-signage-melbourne-victoria/feed/ 8 20837
Ardeer, Sunshine West and high voltage power lines https://wongm.com/2022/05/ardeer-sunshine-west-community-action-high-voltage-power-lines/ https://wongm.com/2022/05/ardeer-sunshine-west-community-action-high-voltage-power-lines/#respond Mon, 09 May 2022 21:30:00 +0000 https://wongm.com/?p=17636 Now you see it, now you don’t – this is the story of the high voltage power lines that were planned to pass through Ardeer and Sunshine West, but thanks to community action never came to be. A mystery My story starts in April 2010, when I paid a visit to Ardeer to photograph the […]

The post Ardeer, Sunshine West and high voltage power lines appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
Now you see it, now you don’t – this is the story of the high voltage power lines that were planned to pass through Ardeer and Sunshine West, but thanks to community action never came to be.

Unused power lines beside the tracks at Ardeer

A mystery

My story starts in April 2010, when I paid a visit to Ardeer to photograph the procession of passing trains bound for Ballarat, and found a row of brand new power poles awaiting the installation of overhead cables.

New poles ready to carry 66 kV lines from Deer Park Terminal Station to Sunshine Zone Substation

I visited again in March 2011, and the poles were still in the same unfinished state.

VLocity 3VL44 and VL38 on the down at Ardeer

And again in September 2011.

N455 leads an up service out of Ardeer

At the time I didn’t think too much about the power lines, but on closer inspection they were nowhere to be seen! So where did they go?

The backstory

As Melbourne’s west has expanded, so has the load placed on the electrical network that serves it – with Keilor Terminal Station bearing the brunt of demand.

500 kV end of the Keilor Terminal Station

So the Australian Energy Market Operator made the decision that a new 220kV / 66kV terminal station should be built to share the load, located beside the existing high voltage power lines at Deer Park.

The new Deer Park Terminal Station at Christies Road in Ravenhall has been completed

As well as a new 66kV / 22kV zone substation to supply the growing suburbs and industry of Truganina.

And a web of new 66kV high voltage power lines to tie together the new and existing zone substations.

66 kV lines outside Sunshine Zone Substation

Local communities caught unaware

However for the residents of Ridgeway Parade in Sunshine West, the appearance of 66 kV power lines along their street in June 2010 caught them by surprise – leading to work being suspended.

Power struggle in Sunshine and Ardeer on lines
Brimbank Leader
1 June 2010
Andre Awadalla

Sunshine West and Ardeer residents have vowed to fight a move to install new overhead power lines in their area.

And while electricity supplier Powercor says it has temporarily suspended work on the project to listen to community concerns, it maintains the project will go ahead.

Sunshine West resident Larissa Stewart said about 70 residents concerned about the overhead power lines gathered at Ridgeway Parade Kindergarten last week.

“People are very angry that this has proceeded without consultation,” Ms Stewart said. She said residents in and around Ridgeway Pde were worried about the health effects of electromagnetic radiation, the visual impact of the powerlines and property values if the power lines were not placed underground.

“It’s going to devalue the properties in the area, absolutely,” Ms Stewart said.

Derrimut state Greens candidate and former councillor Geraldine Brooks said an unanimous resolution was passed at last week’s meeting that the community wanted the lines placed underground.

Ms Brooks said Powercor had failed to consult with residents and that some of the power poles were only 10m from houses and 8.5m from the railway line, raising safety concerns.

Powercor spokesman Damien Batey said it was “regrettable” that Powercor had not consulted with residents before work began.

He said that was an “oversight”, rather than a deliberate attempt to withhold information.

Mr Batey said work had been suspended “while we work through community concerns”.

But he said that while placing the power lines underground had been considered, it would be “incredibly cost prohibitive”.

Mr Batey also said that a report Powercor had commissioned from an independent consultant showed that there was “a very, very low risk of any health concerns” as a result of the power lines and that any electromagnetic radiation would be “well below” levels of acceptable exposure.

The project will supply power to growing industrial areas in the west and supplement residential power.

With the Brimbank City Council becoming involved in the fight

Powerlines raise ruckus
The Advocate
26 July 26, 2010
Ruza Zivkusic

As Sunshine West and Ardeer residents step up their fight against the installation of new overhead powerlines in the area, an electricity supplier is planning a beautification program to replace trees it removed.

Brimbank Council is negotiating with Powercor to pay $40,000 for street tree planting. The company had removed three trees on Ridgeway Parade because of the risk of them growing into the overhead lines.

Powercor spokesman Damien Batey said the company would present its plans to residents shortly.

Ardeer resident Larissa Stewart yesterday met with concerned neighbours to form an action group to oppose the overhead lines.

Work has been stopped since last month while Powercor conducts consultation. Residents fear electro-magnetic frequency emissions from the lines will result in increased health risks.

Ms Stewart claimed residents’ calls and emails to Powercor were going unanswered. “A lot of us have made multiple attempts to make phone calls but haven’t had any response.

“Powercor has only distributed letters to our residents about their intentions in English, but 90 per cent are from non-English-speaking backgrounds and most are Vietnamese.”

Installation of the lines by Powercor will supply power to Paramount Industrial Park and nearby residential areas. The council last week adopted a report to continue advocating on behalf of the community affected by the proposal, requesting that Powercor minimise the impact of the powerlines on streetscape character through tree planting and alternative route alignments.

But Ms Stewart repeated calls for the lines to be placed underground.

“They wouldn’t have the lines through the eastern suburbs 13 kilometres from the CBD,” Ms Stewart said. “They have put powerlines in an open space area where we used to walk the dogs and the kids and have a little bit of open space.

“We thought we’d buy something we knew. We knew where the railway line was, where the schools and the facilities are and all of a sudden, nine years down the track, our happy little community has an upheaval because of a big organisation.”

Mr Batey said the lines had been designed to ensure an “extremely low” level of EMF emission, representing less than 0.7per cent of the prescribed maximum levels of exposure from the relevant authorities.

“This has been determined through scientifically proven research and validated by independent experts,” he said.

Residents sharing worries about reduced property values and health concerns in a letter to the editor.

Residents call for powerline action
Sunshine Star Weekly
24 August 2010

As concerned residents, we are protesting Powercor’s proposed High Voltage overhead powerline through the suburbs of West Sunshine and Ardeer. To this effect, we would appreciate your support in once again highlighting this urgent matter.

The 66kV powerline, proposed to facilitate the new industrial estate west of the Ring Rd in Ardeer, will both endanger the health of the community and its children and slide the area into an urban wasteland of unsightly powerlines and falling real-estate values, effectively condemning that part of Sunshine and Ardeer into an almost third world environment for years to come.

Powercor’s refusal to recognise the potential dangers of overhead High Voltage power and its refusal to “underground” the line is alarming.

While Powercor supports its intended action by claiming to be guided by World Health recommendations and Australian standards, it refuses to recognise these guidelines as being outdated (1998) and in need of urgent revision.

Recent epidemiological research, including WHO findings, has confirmed an undeniable association between electro-magnetic exposure and childhood leukaemia and many world authorities have both expressed concerns about the current inadequate limits of allowable EMF emissions and called for precautionary measures in the installation of High Voltage power.

Furthermore, while Powercor claims that “undergrounding” is too expensive and that regulations require it to pursue “the lowest cost options”, it turns a blind eye to the costs imposed on the community through devaluation of homes and environment and potential medical costs in treating EMF induced leukaemia, not to mention the emotional cost of suffering, sickness and loss of loved ones to cancer.

One can only ask the question: what price do we place on human life? For a multi-national company with huge yearly profits, it seems that safeguarding the health of our children and environment is far less important than protecting profits.

As a major utility and licence holder, Powercor owes the community a duty of care. We plead that Powercor reconsiders its options and exercises a more precautionary attitude by “undergrounding” the line.

Elizabeth and Micheal Kononada,
West Sunshine.

And unhappy with the alternative options presented by Powercor.

Powercor’s options fail to allay fears
The Advocate
27 September 2010
Monique Ebrington

Brimbank residents marched to Parliament House last week to protest against alternatives offered by electricity distributor Powercor.

More than 25 Ardeer and Sunshine West residents took part in the protest, which followed a community meeting of residents, councillors, local MPs and Powercor representatives on September 14. The meeting came after lengthy consultations with residents concerned about the potential impacts of new above-ground powerlines on their health and on house prices.

Rather than the initial plan to run above-ground powerlines along Ridgeway Parade in Ardeer, Powercor put forward three alternative options to residents.

Powercor spokesman Hugo Armstrong said the alternative choices were “the only realistic options to solve the issue”.

The options are a change to the route of the overhead powerlines, an increase to the height of the structures, or for the lines to be placed underground. Ardeer resident Larissa Stewart said residents were “unhappy” at the options presented to them.

“Absolutely none of the alternatives have Powercor fully funding the project,” Ms Stewart claimed. “Powercor is a privately owned company that reports to shareholders. They are asking the council to fund infrastructure that’s going to return funds to private shareholders.”

She said Brimbank was a community that desperately needed funding for other services.

“I think one of the reasons the community is so passionately against it is because it takes money away from a community that doesn’t have a lot.”

A Powercor spokesman said that due to regulations, Powercor could fund $2 million towards the underground option and Brimbank Council or residents would have to fund the remaining $900,000. He said the other options did not require co-contribution. “We simply cannot underground every powerline in the state and expect our customers to absorb those costs.”

The existing powerlines servicing Ardeer and Sunshine West are operating at 30 per cent above the optimal load.

Powercor said residents could expect power outages over summer if a new high-voltage circuit was not provided to the region.

But somewhat surprisingly, a year later residents got the underground power lines they wanted, thanks to extra funding from the state government.

It’s power to the people
Brimbank Weekly
22 November 2011
Benjamin Millar

Ardeer and Sunshine West residents have successfully campaigned for high-voltage powerlines to be placed underground, proving people power can prevail over corporate giants.

Families gathered at Ardeer Community Park on Saturday to celebrate their win following the completion of recent major works in the area.

Geraldine Brooks, of the Ardeer and Sunshine West Powerlines Action Group, said the controversial 66,000-volt powerline proposal was sprung on the community by electricity distributor Powercor without concern for residents’ health and visual amenity.

“Sixty-six thousand-volt powerlines through our community would have exposed families to high electromagnetic field levels,” she said.

Residents learned of the lines only when Powercor began erecting poles on Ridgeway Parade early last year.

“We found that completely unacceptable and made sure the proponent, Powercor, got this message loud and clear throughout a year of community meetings, protests, letter-writing, petitions and publicity,” Ms Brooks said.

Following pressure from residents and Brimbank Council, the State Government’s Powerline Relocation Committee agreed in June to help Powercor fund the $2.8million project.

The underground lines will supply power to Paramount Industrial Park in Deer Park and nearby residential areas.

Western Metropolitan Greens MP Colleen Hartland said the campaign was a great example of people power. “This community forced a multinational company to back down – it just goes to show what can be achieved when the local community works together.”

Footnote – another struggle

Hot on the heels of the fight against high voltage power lines, in 2013 the residents of Ridgeway Parade had a new project on their doorstop – Regional Rail Link.

They were worried about the increased number of trains using the existing railway.

Posters from the 'Fix the Links' Residents Rail Action Group opposite Ardeer station

Rail noise.

Posters from the 'Fix the Links' Residents Rail Action Group opposite Ardeer station

Tall noise walls along the rail corridor.

Posters from the 'Fix the Links' Residents Rail Action Group opposite Ardeer station

And delays to road traffic at the Fitzgerald Road level crossing.

Posters from the 'Fix the Links' Residents Rail Action Group at the Fitzgerald Road level crossing

And so formed the “Fix the Links Residents Rail Action Group” to campaign for their interests.

Group for rail link but want proper planning
Sunshine Star Weekly
30 October 2012
Vanessa Valenzuela

More than 100 angry Brimbank residents rallied at Ardeer Station last weekend, calling on the Regional Rail Link Authority to postpone construction work on the multi-billion dollar project.
The ‘Fix the Links’ Residents Rail Action Group voiced their concerns about an increase in noise, pollution and traffic congestion in the area as a result of the Regional Rail Link.

Brimbank resident Maurice Sibelle said the group wanted the rail link to go ahead, but were asking the authority to address their concerns before commencing construction work.

“There are some misconceptions in the community that we are opposed to the Regional Rail Link but we are not,” Mr Sibelle said.

“We want to present to the community and all interested parties that there is an intelligent response to what the government is doing and they are rushing ahead with this project.”

“Our fear is that it will take so long to adopt the policy that the RRL will be finished and the money will be spent, and we will be left with is the problem that is still there, and there is no plan to fix it,” he said.

Greens MP Colleen Hartland said there are a number of serious and significant community concerns regarding the Regional Rail Link that need to be addressed.

“I share the key concerns of the community and the Fix the Links residents group – noise, diesel pollution and access issues at rail crossings,” Ms Hartland said.

“Noise and diesel pollution concerns have been raised by communities all along the rail corridor from West Melbourne all the way to Deer Park, and these concerns are justified.

“Electrifying the line and running modern electric trains would resolve both of these issues to a large extent.”

Brimbank Council’s General Manager of Infrastructure and Environment Paul Younis said council would seek to facilitate consultation between the Regional Rail Link Authority, ‘Fix the Links’ and other residents relating to concerns about the railway corridor between Sunshine and Deer Park.

“Council continues to play a strong advocacy role on behalf of the community in order to realise optimal community outcomes from the Regional Rail Link project,” Ms Younis said.

“Further consultation is planned once the Department of Transport’s Draft Passenger Rail Infrastructure Noise Policy is finalised at the end of the year.”

A spokesperson for the RRL said the project will continue to comply with all relevant environmental legislation, standards and guidelines, including those on noise and air quality.

For more information about the ‘Fix the Links’ action group visit fixregionallraillink.blogspot.com.au

But this time around, the state government was not on their side – they built the massive steel noise walls along the rail corridor anyway.

Steel noise walls line the railway parallel to Forrest Street

And the level crossing at Fitzgerald Road was left untouched, despite the massive delays to road traffic caused by the extra trains now passing through it.

Transit Systems bus #50 5993AO on route 427 waiting at the Fitzgerald Road level crossing at Ardeer

A situation not addressed until 2020, when the Fitzgerald Road level crossing removal project was given the go ahead.

VLocity VL70 and VL40 on the up at Fitzgerald Road, Ardeer

Footnote: a few more gory details

The two underground feeders are ‘SU024’ and ‘SU032’ – running 2.861 kilometres and 3.319 kilometres respectively.

In 2015 the Sunshine zone substation served by the underground power lines was itself upgraded.

Sunshine zone substation refurbishment

Sunshine Zone Substation (SU) supplies electricity to over 25,000 customers including domestic, commercial and industrial in the Sunshine, Ardeer, Deer Park, Laverton North, St Albans, Caroline Springs and Derrimut areas.

In response to the existing SU transformers nearing end of life and additional load requirements brought on by new data centres in the area, Powercor commenced a program to refurbish and redevelop the zone substation over the 2012 to 2017 period.

The SU zone substation comprised four transformers and outdoor discrete HV switchgear. Two transformers are in service and a group of two smaller transformers are available for contingency operation. The transformers have no voltage regulation and are of limited use. All transformers at the station are aged and in poor condition.

The HV switchgear (outdoor circuit breakers) are aged and also in poor condition. The HV bus structure is currently supported as a long term temporary measure with scaffolding. Other station components including the capacitor banks, buildings and fences are in poor condition.

To finalise the redevelopment of the SU zone substation, Powercor needs to decommission and remove two of the old transformers and associated equipment. This is contingent upon the establishment of Deer Park Terminal Station (DPTS) to enable load transfers.

As part of the works for the new Deer Park Terminal Station.

Powercor undertook a joint Regulatory Test with Jemena Electricity Networks and the Australian Energy Market Operator (AEMO) to address a system limitation at the Keilor Terminal Station (KTS), and on the sub-transmission lines from KTS that serves the Melton (MTN), Sunbury (SBY) and Sydenham (SHM) zone substations. SBY and SHM are zone substations for Jemena.

The final report was published on 1 May 2012 which recommended the construction of a new terminal station at Deer Park (DPTS). The regulatory test demonstrates that the works are prudent and efficient and that the option selected maximises the net economic benefit to consumers. Other key elements of the report include:

• construction of 66kV sub-transmission lines from DPTS to a new zone substation at Truganina (TNA);
• construction of 66kV sub-transmission lines to transfer the existing MLN zone substation to DPTS, relieving constraints at KTS. As part of this work, the existing KTS to MLN and MLN to SBY
66kV sub-transmission lines will be reconfigured to bypass MLN and establish a KTS to SBY2 line. This maintains the required third supply to the SHM and SBY 66kV loop exiting KTS, which also
supplies Gisborne (GSB) and Woodend (WND) zone substations; and
• construction of 66kV sub-transmission lines to transfer existing Sunshine zone substation (SU) to DPTS, relieving constraints at KTS. As part of this work, the existing KTS to SU2 and SU to
Sunshine East (SSE) 66kV sub-transmission lines will be re-configured to supply SSE via its own loop from KTS.

With the upgraded distribution network commissioned in 2017.


Powercor diagram

Further reading

Post retrieved by 35.215.163.46 using

The post Ardeer, Sunshine West and high voltage power lines appeared first on Waking up in Geelong.

]]>
https://wongm.com/2022/05/ardeer-sunshine-west-community-action-high-voltage-power-lines/feed/ 0 17636
On the trail of a high voltage transmission line https://wongm.com/2022/02/on-the-trail-of-a-high-voltage-transmission-line/ https://wongm.com/2022/02/on-the-trail-of-a-high-voltage-transmission-line/#comments Mon, 21 Feb 2022 20:30:00 +0000 https://wongm.com/?p=19158 The other day I was reading The Age and saw a photo of scene I swear I’ve seen before, but I couldn’t put my finger on the exact location. So let’s go chase down some high voltage power lines, and see where they take us. Nicole Cleary photo via The Age On the trail The […]

The post On the trail of a high voltage transmission line appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
The other day I was reading The Age and saw a photo of scene I swear I’ve seen before, but I couldn’t put my finger on the exact location. So let’s go chase down some high voltage power lines, and see where they take us.


Nicole Cleary photo via The Age

On the trail

The massive pylons and quad bundle conductors look just like those on the 500 kV twin circuit Moorabool-Portland transmission line I wrote about the other month.

500 kV twin circuit Moorabool - Portland transmission line at Berrybank, Victoria

I’ve been a fan of this transmission line for years.

T357 and V/Line power van PCJ491 dwarfed by the power lines at Gheringhap

The lush green grass suggested dairy country around Mortlake, not the wheat fields of the Pleurisy Plains.

500kV transmission line from Moorabool to Portland parallels the Hamilton Highway near Cressy

But there was one big clue – the pair of transposition towers in the background.

A transposition tower is a transmission tower that changes the relative physical positions of the conductors of a transmission line in a polyphase system. A transposition tower allows these sections to be connected together, while maintaining adequate clearance for the conductors. This is important since it distributes electrical impedances between phases of a circuit over time, reducing the problem of one conductor carrying more current than others.

Double-circuit lines are usually set up with conductors of the same phase placed opposite each other. This reduces the reactance due to mutual inductance; the reactance of both circuits together is less than half that of one circuit. For example, a section of a line may be (top-to-bottom) phases A-B-C on the left, also phases C’-B’-A’ on the right. The next section may be B-C-A on the left, also A’-C’-B’ on the right. Therefore, the rotation on each side of the tower will be opposite.

But would a set of transposition towers be big enough to spot on Google Maps?

And away I go

My initial theory was that the photo couldn’t be taken *that* far from Melbourne or off a main road – normal people don’t go driving for hours down bush tracks just to photograph power lines – so I made a virtual visit to the Moorabool Terminal Station outside Geelong.


Google Maps

My first location of note on Google Maps – a hub of activity outside Cressy, where the transmission lines were being repaired.


Google Maps

Six pylons came tumbling down to earth in January 2020 following extreme winds.


ABC News photo

The outage shut down the Portland aluminium smelter, until temporary repairs were completed to allow power to be restored.


The Standard photo

Then off across empty plains until Lismore – where I found two parallel single circuit pylons.


Google Maps

But this wasn’t the transposition towers I was looking for, but somewhere I’ve been meaning to visit in person – the spot where the 500 kV line crosses over the single circuit Ballarat to Terang 220 kV line.


Google Street View

As I continued west, the paddocks started to turn green, and I found another place I’m yet to visit – Mortlake Terminal Station.


Google Maps

And the fossil gas fired Mortlake Power Station that relies on it.


Origin Energy photo

And finally something that matched what I was looking for – a pair of single circuit transposition towers in the middle of a twin circuit transmission line, outside the locality of Willatook.


Google Maps

Following Google Street View along Malseeds Road found the transposition towers.


Google Street View

But given the transmission line turns to the right before reaching the transposition towers, I needed to head west – Willatook-Warrong Road was the next road to take.


Google Street View

Now to see if it was the same set of pylons.


Nicole Cleary photo via The Age

And boom .


Google Street View

A match!

And one last detail

The little sign in the background of the original photo looked like a ‘Danger: Gas Pipeline’ sign, but the only gas network diagrams I could find lacked sufficient detail to confirm.


AEMO gas pipeline network map

And over at Open Infrastructure Map the only feature at the location was the 500 kV transmission line I’d been following since Moorabool.


Open Infrastructure Map

So an adventure for another day.

Further reading

Some more detail on the 2020 transmission line pylon collapse at Cressy.

Post retrieved by 35.215.163.46 using

The post On the trail of a high voltage transmission line appeared first on Waking up in Geelong.

]]>
https://wongm.com/2022/02/on-the-trail-of-a-high-voltage-transmission-line/feed/ 2 19158
Backup generators and the 1982 New South Wales power crisis https://wongm.com/2020/06/1982-new-south-wales-power-crisis-backup-gas-turbines/ https://wongm.com/2020/06/1982-new-south-wales-power-crisis-backup-gas-turbines/#comments Mon, 08 Jun 2020 21:30:00 +0000 https://wongm.com/?p=12831 In Australia power generation has become another front in the culture wars, as backers of coal fired power stations fight the growth of renewable solar and wind power, blaming them for any minor power outage. But back in 1980s New South Wales far worse power restrictions were put into place – and failed coal fired […]

The post Backup generators and the 1982 New South Wales power crisis appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
In Australia power generation has become another front in the culture wars, as backers of coal fired power stations fight the growth of renewable solar and wind power, blaming them for any minor power outage. But back in 1980s New South Wales far worse power restrictions were put into place – and failed coal fired power stations were to blame.

The story starts with the construction of Liddell Power Station in the Hunter Valley by the Electricity Commission of New South Wales (Elcom). The first of four 500 megawatt generators was completed in 1971, followed by two more in 1972, and the fourth in 1973. The complex was the first major power station in New South Wales to be built inland, and at the time of its completion was the most powerful generating station in Australia.

However a few years later all was not well at Elcom – maintenance on the generating system was being deferred, and the massive scale of new power stations left the system without reserve capacity should any of the units go off line.

This came to a head when in March 1981, when a stator winding fault at Liddell took one of the units out of service. Initially the Snowy Mountain Scheme was used to supply peak electricity load, but an ongoing drought had reduced the amount of water available, which led to the introduction of power restrictions in late June.

In November 1981 the situation worsened, when two more generators at Liddell suffered identical stator winding faults, with further power restrictions imposed for twenty days in December 1981, and twenty-six days in March-April 1982.


Canberra Times – 1 April 1982

Leaving both industry and households in the dark.

In one day of power rationing to industry it was estimated that 253,000 workers were stood down after 7,000 factories closed at a cost of $25 million to NSW industry.

Householders were restricted to half the normal lights on in a house, no air-conditioning, no radiators and, despite possible health risks, only two hours a day for filtering swimming pools.

To fill the gap, 300 MW of gas turbine generators was hurriedly acquired.

Twelve 25MW gas turbines were purchased by the Electricity Commission of New South Wales in 1982 to assist in meeting demand during the electrical energy crisis in that year resulting from the failure of alternator windings in three generating units at Liddell Power Station.

The units were connected to the State network in April, May and June, 1982. Total capital cost was $89 million. Two units are located at Bunnerong, two at Port Kembla, four at Eraring and four at Koolkhan near Grafton.

All gas turbines were used during the energy crisis in the period April to September, 1982. Operating times totalled approximately 5,000 unit hours, 85 per cent of the energy being generated using natural gas at Bunnerong and Port Kembla.

That were expensive to run.

For statistical and costing purposes a fuel consumption of 8.3 tonnes of distillate per hour is an average value recorded for each gas turbine when operating at full load.

The gas turbines at Bunnerong and Port Kembla use natural gas as fuel and for these units the gas consumption is 15.0 MJ/GWh.

In 1982 the cost of distillate was $267 to $3 10 per tonne. These values have been used to calculate a distillate fuel cost of $88 per MWh.

Under the current gas contract, fuel cost when burning natural gas is $84 per MWh for units at Bunnerong and Port Kembla.

The cost of running a gas turbine at full load (25 MW) for one hour is:
(a) natural gas fuel – $2,100 on current gas price.
(b) distillate fuel – $2,200 on 1982 fuel price. $3,875 on 1986 replacement fuel price.

With power restrictions finally averted by the commissioning of the first 660 MW unit at the coal fired Eraring Power Station in March 1982.

So what happened to the gas turbines?

After the power crisis had ended, some in parliament thought they should be sold off.

In 1982, in a panic move after the blackouts of 1981 the commission, at the Government’s insistence, purchased twelve gas turbines at a cost of $130 million. These turbines are not in use, have never been used and have no use, because they are too costly to operate.

The turbines should be sold to recoup the $130 million paid for them. The excuse that the turbines are to be used for a black start is not acceptable. It is absolute nonsense to give that excuse, and the Minister well knows it.

But Elcom did make use of the gas turbines in times of peak demand.

During autumn 1983 the natural gas turbines at Bunnerong and Port Kembla were operated due to reduced water storages in the Snowy Mountains Hydro-Electric Scheme as a result of a prolonged drought. Operating hours totalled approximately 1,700 unit hours.

In addition, gas turbines have been operated for brief periods, as follows:

  • Koolkhan to assist with a local supply problem in April 1984.
  • Bunnerong and Port Kembla to assist the State Electricity Commission of Victoria following plant failures in that State.
  • At all locations on one day in March 1983, as a result of loss of thermal generating plant due to switchboard flashovers.
  • At all locations for three days during February 1986, during the coalminers’ strike.
  • For one hour each month as a test on performance.

The units installed at Koolkhan have allowed deferment of some 330 kV transmission line projects in the area north of Armidale, with resultant cost savings of about $2 million.

Capable of generating at full load within 12 minutes of start-up, the turbines were seen as ideal emergency backup despite average annual maintenance costs of $3,200 per unit, which saw Elcom redeploy them to other parts of the network.

A review has been undertaken of the need to retain the gas turbine units.

Present forecasts of load growth indicate that there could be a need for the installation of additional combustion turbines towards the middle of the 1990’s and at this stage it has been decided not to sell any of the gas turbine units.

The benefit to the Commission of relocating gas turbines on the State grid would far outweigh the return obtained by selling this plant.

Action is in hand to relocate the Bunnerong units to the Upper Hunter district to provide “black start” capability for Liddell and Bayswater Power Stations, and it is proposed to relocate the Port Kembla units to Broken Hill as emergency standby supply in case of any failure in the transmission system.

The two units at Bunnerong Power Station were removed by 1984, and recommissioned between the Bayswater and Liddell Power Stations in 1988. They passed to Macquarie Generation as part of the breakup of Elcom, and remain in service today as the ‘Hunter Valley Gas Turbines’ owned by AGL Macquarie.


Google Earth 2020

The two units at Port Kembla were also relocated as planned to Broken Hill, being recommissioned in 1989.

Today it serves as a backup electricity supply to the isolated city of Broken Hill, should the single 220 kV transmission line be down for maintenance or an unplanned outage.


Google Earth 2020

Four gas turbines at Koolkhan fill a similar role, supplying to the far north coast of NSW should there be an outage on the 330 kV line from down south. Around 2000 Elcom successor Pacific Power decommissioned the gas turbines, which were sold off and exported to the USA. The site now lays empty.


Google Earth 2004

And finally, the four turbines at Eraring. They were passed to Elcom successor Eraring Energy, which operated two units as the ‘Northern Gas Turbines’ until they were decommissioned in 2001.

The site is now empty, but Eraring Energy did commissioned a 40 MW rated ‘Emergency Black Start Gas Turbine‘ in 2007 to meet the same role.


Google Earth 2020

Footnote: modern day equivalents

During the 2017-18 summer the Australian Energy Market Operator hired 105 diesel-powered generators that were setup at the Energy Brix Power Station site in Morwell, to supply up to 110 MW of electricity to Victoria in an emergency. They were never used, and did not return.


Aggreko Australia photo

In 2017 the South Australian government did something similar, purchasing nine new aero-derivative turbines to supply up to 276 MW of electricity to the state. After laying idle during the 2017-18 summer, they saw first use in January 2019, only be be sold to the private sector later that year.


South Australian government photo

Footnote: how did I get here?

The genesis of this post was a simple train photo, captioned “8119 and 8131 unloading at Eraring Power Station Coal Loop. 29 January 1994“.

To which someone replied:

Four 25mw diesel turbines just right of centre. I worked on some electrical modifications to these in about 1981.

And so I went this rabbit hole.

Sources

Post retrieved by 35.215.163.46 using

The post Backup generators and the 1982 New South Wales power crisis appeared first on Waking up in Geelong.

]]>
https://wongm.com/2020/06/1982-new-south-wales-power-crisis-backup-gas-turbines/feed/ 10 12831
A history of synchronous condensers in Victoria https://wongm.com/2020/05/history-synchronous-condensers-state-electricity-commission-victoria/ https://wongm.com/2020/05/history-synchronous-condensers-state-electricity-commission-victoria/#comments Mon, 25 May 2020 21:30:58 +0000 https://wongm.com/?p=12857 In the past decade wind and solar generation has been displacing older coal fired power stations in Australia, with the stability of the electricity grid coming into question. One of the proposed solutions is something called a synchronous condenser – a technology that the State Electricity Commission of Victoria took advantage of fifty years ago. […]

The post A history of synchronous condensers in Victoria appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
In the past decade wind and solar generation has been displacing older coal fired power stations in Australia, with the stability of the electricity grid coming into question. One of the proposed solutions is something called a synchronous condenser – a technology that the State Electricity Commission of Victoria took advantage of fifty years ago.

Codrington Wind Farm

So what am I even on about?

ABC News looked into the topic of grid stability back in 2017.

Power grids are complex machines, dependent on the laws of physics. The national grid is designed to operate at a consistent frequency of 50 Hertz, or 50 cycles a second.

Traditional coal, gas and hydro power stations are considered “synchronous” because they use turbines or spinning wheels to produce electricity. Those spinning parts need to stay close to 50Hz to help keep the grid in synch.

But most of Australia’s installed wind and solar systems are not considered to be. That’s because they use inverters to connect to the grid, rather than spinning wheels.

If too much power is fed in relative to demand, the frequency will increase. If demand outstrips supply, the frequency drops. Regulators rely on a suite of technologies to help keep the grid frequency close to 50Hz.

Synchronous condensers are one of the technologies used to maintain the frequency of the grid, with Energy Networks Australia explaining the technical details in their piece, The age of the syncons.

What is system strength?

System strength is important as it relates to the ability of the power system to withstand changes in supply or demand while maintaining stable voltage levels.

When system strength is low, generators may not be able to remain connected to the grid, control of the power system voltage level becomes more difficult and protection systems (which control and maintain the safe operation of the network) may not operate correctly. This can result in supply interruptions to customers.

System strength is typically provided by synchronous generation such as coal or gas-fired generation or pumped hydro.

What are synchronous condensers?

Synchronous condensers are an old technology, commonly used as far back as the 1950s to stabilise power systems.

They are large machines which spin freely and can absorb or produce reactive (Alternating Current – AC) power in order to stabilise and strengthen a power system.

Synchronous condensers help when there are changes in load as they increase network inertia. The kinetic energy stored in a synchronous condenser contributes to the total inertia of the power system and is beneficial from a frequency control perspective.

What is inertia?

Inertia in the energy system refers to the continuous momentum of energy typically provided by the large spinning turbines of synchronous generators like large coal-or gas-fired power stations. This type of generation helps withstand changes in generation output and load levels to keep the system stable.

The retirement of synchronous power plants and more renewable generation coming into the energy system means there is less inertia available, so flexibility or stability must be found elsewhere in the system to back it up.

And their usage in Victoria

Until the 1990s the electricity network in Victoria was managed by a single government entity – the State Electricity Commission of Victoria.

State Electricity Commission of Victoria warning sign

Brown coal from the Latrobe Valley was their fuel of choice.

Hazelwood Power Station - 1960s chic

But despite all of the old fashioned spinning metal in their power stations, in 1966 the SECV installed a 750 rpm +125 -75 MVar at 22 kV capacity synchronous condenser at the Templestowe Terminal Station in north-east Melbourne.

A few years later a second synchronous condenser was installed at the Fishermans Bend Terminal Station, south of the Melbourne CBD.

Looking down on the Bolte Bridge and Yarra River

And in 1971 a third unit at Brooklyn Terminal Station, in Melbourne’s west, with a salient pole design rotating at 750 rpm, with a rating of +110 -64 MVar at 14.5 kV, and a short time overload rating of 140 MvAr (10 min).

Front gate to the electrical substation

Following privatisation the reliability of the synchronous condensers declined, with availability falling below the 91% target in 2003. As a result network operator SP AusNet launched a refurbishment program to address degradation of stator winding sidewall and rotor pole insulation, but by 2013 only the unit was Brooklyn had been upgraded.

As a result reliability declined, with the end coming in October 2016.

AusNet Services and AEMO agreed in October 2016 that it was prudent to retire, rather than replace, these three synchronous condensers on the transmission network. These assets were in extremely poor condition and studies confirmed that their replacement would not have provided a net market benefit.

Since the agreement to retire the synchronous condensers, all three units have failed due to their poor condition. Given that the synchronous condensers were due to be retired by 1 April 2017, AusNet Services and AEMO agreed that it was not efficient to repair and return the synchronous condensers into service.

With SP AusNet realising an additional $7.0 million depreciation charge in their 2017 annual report.

Everything old is new again

In 2017 synchronous condensers hit the news, when AGL flagged them as one part of their transition away from coal fired power.

Liddell Power Station is a 2000 MW black coal fired thermal power station, commissioned between 1971-73. The site also includes associated infrastructure required for power generation, including water, coal and transmission plant.

In April 2015 AGL released a revised Greenhouse Gas Policy. The Policy outlined AGL’s commitment to the decarbonisation of our electricity generation portfolio, confirming closure dates for our coal-fired power stations. The announced closure date for Liddell is the end of 2022.

AGL believes that the installed capacity and energy output from Liddell is best replaced with lower emissions and more reliable generation, with a longer lifespan.

As part of our NSW Generation Plan we are investigating the use of one Liddell generating unit as a synchronous condenser.

As part of new solar farm proposals.

Many other wind and solar projects in Victoria and elsewhere are having to go back to the drawing board because of connection requirements the developers either ignored, or didn’t know about.

The issue is most acute in western Victoria, but is also being felt in northern Queensland and south-west NSW.

Many new projects are being told that they face significant curtailment without either adding battery storage or old-style machinery known as synchronous condensers to deal with system strength issues.

Both options are causing headaches for developers, because either way they are trashing their financial models, and could cause extensive delays to projects that many expected would begin construction anytime soon.

As a high cost fix for system flaws.

RenewEconomy has been told that a synchronous condenser could add $8-$10 million in costs to projects already tight on margins. A group of solar farms in north-west Victoria have been told, RenewEconomy understands, that their additional costs could total $60 million.

And to reinforce the South Australian power grid.

As more energy sources such as wind and solar are connected to the grid, traditional power generation sources such as gas-fired units, operate less often. This has created a shortfall in system strength which was declared by the Australian Energy Market Operator (AEMO) on 13 October 2017 and a shortfall in inertia which was declared on 24 December 2018.

A secure power system needs adequate levels of system strength and inertia, which to date have been provided by traditional synchronous generators.

Following an analysis of these options, the installation of synchronous condensers on the network was determined to be the most efficient and least cost option to ensure there is adequate system strength and inertia.

On 20 August 2019, the AER approved $166 million to fund the capital cost of delivering the synchronous condenser solution.

The first two of four planned synchronous condensers will be installed at the Davenport substation in mid-2020 and the second two will be installed at the Robertstown substation by the end of 2020. They will be commissioned by early 2021.

How things change in the course of two years!

Update for 2022

In July 2022 a 60Mvr synchronous condenser supplied by GE has been switched on at the Murra Warra wind farm in the West Murray region, enabling the project to increase export capacity to 150MW, before moving towards full capacity of 209MW.

The synchronous condenser was required as part of the since abandoned “do no harm” rules that required new generation projects to address system strength issues in the transmission network. This is now the responsibility of network operators.

Footnote: alternate sources of voltage support

Static VAR compensators are another way of stabilising the electricity grid.

A static VAR compensator (SVC) is a set of electrical devices for providing fast-acting reactive power on high-voltage electricity transmission networks. SVCs are part of the Flexible AC transmission system device family, regulating voltage, power factor, harmonics and stabilising the system.

A static VAR compensator has no significant moving parts (other than internal switchgear). Prior to the invention of the SVC, power factor compensation was the preserve of large rotating machines such as synchronous condensers or switched capacitor banks.

Four SVC units are installed on the SP AusNet Network in Victoria – two +100 -60 MVar capacity units at Rowville Terminal Station, and one +50 -25 MVar unit at each of Kerang Terminal Station and Horsham Terminal Station.

Installed by the SECV during the mid-1980s and with a technical life of between 40 and 60 years, the control systems are now obsolete technology unsupported by the manufacturer, so an upgrade program is underway to replace them with modern equipment.

Footnote: and something really fruity

Down at Wonthaggi is a real power hog – the Victorian Desalination Plant.

It is supplied with electricity by a 88 kilometre long twin circuit 220 kV AC underground transmission line – the longest of its type in the world.

Underground 220 kV transmission line at Clyde that serves the Victorian Desalination Plant

With the underground cable run requiring something odd at the halfway point – a ‘reactive compensation station’.

Electrical transmission infrastructure at The Gurdies for the Victorian Desalination Plant

The yard full of high voltage switchgear contains three 52 MVAr oil-filled shunt reactors to compensate for the capacitance of the underground cables.

Electrical transmission infrastructure at The Gurdies for the Victorian Desalination Plant

Post retrieved by 35.215.163.46 using

The post A history of synchronous condensers in Victoria appeared first on Waking up in Geelong.

]]>
https://wongm.com/2020/05/history-synchronous-condensers-state-electricity-commission-victoria/feed/ 19 12857
High voltage power lines to nowhere https://wongm.com/2018/01/high-voltage-power-lines-to-nowhere/ https://wongm.com/2018/01/high-voltage-power-lines-to-nowhere/#comments Mon, 15 Jan 2018 20:30:00 +0000 https://wongm.com/?p=9280 On the outer eastern edge of Melbourne there is a curious piece of infrastructure – a high voltage power line to nowhere. So why was it built, and why is it currently sitting idle? Running south-west from Coldstream to Templestowe, via Chirnside Park, Wonga Park and Warrandyte, I was first tipped off to the existence […]

The post High voltage power lines to nowhere appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
On the outer eastern edge of Melbourne there is a curious piece of infrastructure – a high voltage power line to nowhere. So why was it built, and why is it currently sitting idle?

Dead end transmission line at Coldstream, Victoria

Running south-west from Coldstream to Templestowe, via Chirnside Park, Wonga Park and Warrandyte, I was first tipped off to the existence of the transmission line by someone who lives in the area.

Transmission lines at Coldstream, Victoria

The path taken was quite easy to see on the Melway – the eastern end is located at tower T293 in Coldstream.

While the western end terminates at tower T342 in Templestowe.

Eventually I paid a visit in person, and the dead-end nature of the transmission line was easy to see.

The northern end at Coldstream is located alongside two 500 kV transmission lines.

Dead end transmission line at Coldstream, Victoria

While the Templestowe end is located among the transmission lines that serve the Templestowe Terminal Station.

Dead end transmission line at Templestowe, Victoria

But unfortunately I was no closer to finding the reasons for the lines laying abandoned, until my recent post on transmission line crossovers. What started with an exploration of power lines in Sydney, expanded to Rowville Terminal Station in Melbourne, and then down a rabbit hole of State Electricity Commission of Victoria reports.

I eventually landed on a 1983 report on transmission lines serving Melbourne by the Natural Resources and Environment Committee. The purpose of the report was as follows:

This report specifically addresses the SEC’s proposal for a 500 000 volt transmission line from Coldstream to South Morang and in particular:

(i) The need for reinforcing transmission to the 500 000 volt terminal stations in the outer metropolitan area;
(ii) The feasible route to be subjected to detailed examination of environmental issues; and
(iii) The recommended process for assessment and approval of the route in this instance.

The report detailed the current state of the high voltage transmission lines linking the power stations of the Latrobe Valley to Melbourne.

The existing transmission system from the Latrobe Valley to the Melbourne metropolitan areas consists of three 220 kV double circuit lines and three 500 kV single circuit lines.

Two of the 500 kV lines were established in the late 1960s on a northern easement in conjunction with the Hazelwood Power Station and supply the western metropolitan area from the Keilor Terminal Station (KTS). The lines were routed via Coldstream and South Morang with one line being on a direct Coldstream to South Morang easement and the other routed via Templestowe to provide for later development of supply for the north-eastern metropolitan area. The easements from Coldstream to South Morang were each approved with capacity for a second circuit, thereby providing for the four incoming 500 kV lines to South Morang.

The third 500 kV line was established in late 1982 on a southern easement via Cranbourne, Narre Warren and Templestowe, in conjunction with commercial service of the completed Yallourn W Power Station and in preparation for service of the initial Loy Yang A units. The planning permission for the section of this line between Hazelwood and Cranbourne included easement provision for two further 500 kV lines. The section between Cranbourne and South Morang was established on an existing easement.

As well as how the SEC planned to add a fourth 500 kV transmission line into the system:

The further 500 kV line from Hazelwood to Melbourne is planned to be established on the southern 500 kV easement adjacent to the existing 500 kV line from Hazelwood to Templestowe. The section of the line between Narre Warren and Templestowe has already been constructed and the Rowville to Templestowe part of this section is temporarily in service at 220 kV.

And the interesting bit – the abandonment of the transmission line between Coldstream and Templestowe.

To achieve connection of the fourth 500 kV transmission line into South Morang, the SEC propose to take the existing second 500 kV line (the southern circuit on the northern easement) directly into South Morang from Coldstream, so as to free up the section between Templestowe and South Morang for inclusion as part of the fourth 500 000 volt line.

The short section on the northern easement between Templestowe and Coldstream would then be left out-of-service until the future establishment of new 500 kV switching stations at Templestowe and Coldstream.

If that wasn’t clear as mud, this diagram depicted the current state, as well as three proposals for adding a fourth 500 kV circuit between Hazelwood and Melbourne.

Abandoning a section of high voltage transmission line sounds like an odd thing to do – something which Mr. R.F. English, resident of the Bend of Islands Environmental Living Zone immediately adjacent to the proposed transmission line easement, pointed out in his submission to the Natural Resources and Environment Committee.

The decision to take the Coldstream to Templestowe 500 kV line out of service until at least the fifth 500 kV line is constructed and required – this would probably be in at least 25 years or more.

As the Coldstream to Templestowe line is approximately 20 kilometres long, and based on $470,000 per km, this would mean a $9 million asset would remain idle and depreciating for 25 years.

This appears to me to reflect a gross planning error in the SEC’s long term plans “to scar the landscape with 500 kV power lines”.

So what ended up happening?

Transmission lines at Coldstream, Victoria

And you guessed it – State Electricity Commission of Victoria got their way, with the fourth 500 kV transmission line being pushed through the Bay of Islands bushland along the “LV1: second Coldstream to South Morang line” route, and the transmission line from Coldstream to Templestowe abandoned.

But will it be used in the future?

Back in the 1980s the SECV believed that a fifth 500 kV transmission line would be required by 1990 to serve the increasing energy demand of Melbourne.

Transmission lines beside the Maribyrnong River at Footscray

But this prediction was overly optimistic – development of the massive 4,00 MW Driffield Project west of Morwell was abandoned follwing a change of government, and the Loy Yang power station petered out at 3,250 MW of the 4,400 MW capacity originally planned.

In 2009 Victorian energy network operator VENCorp dusted off the old SEC plans, in their ‘Vision 2030’ document:

Development of eastern corridor distribution

A new (fifth) 500 kV power line from the Latrobe Valley to Melbourne via the Northern easement terminating at Templestowe via Coldstream, and establishment of new 500 kV switching stations at Coldstream and Templestowe (140 km). This line would incorporate the currently unused 500 kV line between Coldstream and Templestowe.

Cost: $460 million

But with the decommissioning Hazelwood power station, no new coal fired power stations on the horizon, and the rapid growth of distributed rooftop solar and battery storage, the need for additional capacity between Melbourne and the Latrobe Valley seems redundant.

And another example

Sent in by a reader – a dead end transmission line outside the Geelong Terminal Station.

The transmission line runs north towards the Moorabool Terminal Station, but terminates a short distance to the south.

My guess – the original 220 kV circuit to Geelong was replaced by parallel 220 kV circuits on a new set of pylons, with a 220 KV circuit to Terang taking over the northern-most part of the easement.

Post retrieved by 35.215.163.46 using

The post High voltage power lines to nowhere appeared first on Waking up in Geelong.

]]>
https://wongm.com/2018/01/high-voltage-power-lines-to-nowhere/feed/ 25 9280
Attack of the mutant electronics – hacking a computer PSU https://wongm.com/2005/07/attack-of-the-mutant-electronics/ https://wongm.com/2005/07/attack-of-the-mutant-electronics/#comments Fri, 22 Jul 2005 07:08:38 +0000 http://wongm.com/2005/07/22/attack-of-the-mutant-electronics This is an post from the olden days – read more about them here. Today I finally finished making the dummy battery I mentioned a while back. I had finished most of it, and it worked fine, but it wasn’t the proper size compared to a proper battery. It was too big to use more […]

The post Attack of the mutant electronics – hacking a computer PSU appeared first on Waking up in Geelong.

Post retrieved by 35.215.163.46 using

]]>
This is an post from the olden days – read more about them here.

Today I finally finished making the dummy battery I mentioned a while back.

I had finished most of it, and it worked fine, but it wasn’t the proper size compared to a proper battery. It was too big to use more plastic, so I used wood instead. Now it is all done, and is now the correct size.

Also, I built this other thing, a mutant computer PSU. It supplies power to your computer (because PSU stands for "Power Supply Unit") I needed a power supply for some other crap, so I hacked away at a computer one. It will not work without being connected to a computer, so I changed it so it would.

In case you ever need to do this, connect pin 14 of the big plug (the green wire) to any of the black wires.

I think that is enough home-built electronics for a while. However, cleaning the shed should be on my agenda…

Post retrieved by 35.215.163.46 using

The post Attack of the mutant electronics – hacking a computer PSU appeared first on Waking up in Geelong.

]]>
https://wongm.com/2005/07/attack-of-the-mutant-electronics/feed/ 2 75